By Nicolas Delgado | volunteer
Hi Dear Donnors,
We are happy to share with you the latest update of this project.
We completed the external insulation and waterproofing of the structure, so no more water inside our building!! We also installed the landscaping grass so that kids can start using the kindergarden's playground.
Right now we are very excited as lots of tasks are getting done simultaneously. We are working on all the exterior and interior finishes of the building as well as the internal insulation with our team of neighbors and volunteers.
We expect the building to look quite different in the coming months.
Tasks completed:
-Waterproofing of exterior roof and ceiling completed.
-External insulation completed.
-Grass placement for landscape.
-Floor finishes for outdoor corridors and classrooms.
Task underway:
-External finish in cement boards.
-Internal insulation.
-Internal ceiling in pvc siding.
-Internal finish in plasterboards.
-600lts Rainwater collection system.
-outdoor corridors' roof structure
Please keep on supporting this amazing project so we are able to show really nice updates in the comming months!
Thank you very much!!!
Engineering Without Borders Argentina.